Retention of title in construction
Typically on construction projects, goods, materials or plant are not paid for until after they have been delivered to site. Even then, the contractual chain may mean that the client pays the main contractor at agreed intervals, and then the main contractor pays sub-contractors and so on.
This can put the supplier at risk, if the buyer (typically the contractor) defaults or becomes insolvent before payment is received. If the contractor has delivered the items and the client has received them in good faith then ownership may be disputed even if the supplier has not been paid in full.
A ‘retention of title’ clause (‘RoT, ‘Romalpa clause’ or ‘reservation of title clause’) allows a supplier to retain ownership of until specified conditions have been met, for example, until payment has been made. This is permitted under the Sale of Goods Act or the Supply of Goods and Services Act which provide that title passes from the seller to the buyer when the parties intend it to, which can be, for example; upon delivery, upon payment or upon use. This can override the general principle that title passes on delivery and can give an unpaid supplier’s title priority over the client’s.
Such clauses need to be clearly worded, it must be established that they prevail over other documentation (such as purchase orders), and they must be drawn to the attention of the contractor and client by the supplier. If the contractor becomes insolvent, or seems likely to become insolvent, the supplier should act quickly to establish their case, giving notice of retention of title, and making clear that payment has not been made.
However, even when properly prepared, retention of tile clauses can be difficult to enforce, as generally, title passes to the client once items are incorporated into the development anyway, irrespective of whether payment has been made, and it can be difficult to establish whether payment has been made, as the client may make stage payments rather than paying in total for specific items.
Other measures a supplier might take to reduce their risk include:
- Checking the financial status of the contractor to assess the likelihood of insolvency before accepting an order.
- Arranging for items to be marked and stored separately to make clear title remains with the supplier.
- Entering into a direct contract with the client.
- Seeking advance payment.
Advance payment can be secured with an advance payment bond and the client’s title established with a vesting certificate, although vesting certificates can be similarly difficult to enforce.
NB: The term ‘Romalpa clause’ refers to the case of Aluminium Industrie Vaassen BV v Romalpa Aluminium (1976) which established the principle of extended reservation of title.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Advance payment bond.
- Materials on site.
- Off site goods and materials.
- Off-site goods and materials - legal issues.
- Owner.
- Parent company guarantee.
- Retention.
- Vesting certificate.
[edit] External references
- BIS, Retention of title.
Featured articles and news
Editor's broadbrush view on forms of electrical heating in context.
The pace of heating change; BSRIA market intelligence
Electric Dreams, Boiler Realities.
New President of ECA announced
Ruth Devine MBE becomes the 112th President of the Electrical Contractors Association.
New CIAT Professional Standards Competency Framework
Supercedes the 2019 Professional Standards Framework from 1 May 2025.
Difficult Sites: Architecture Against the Odds
Free exhibition at the RIBA Architecture Gallery until 31 May.
PPN 021: Payment Spot Checks in Public Sub-Contracts
Published following consultation and influence from ECA.
Designing Buildings reaches 20,000 articles
We take a look back at some of the stranger contributions.
Lessons learned from other industries.
The Buildings of the Malting Industry. Book review.
Conserving places with climate resilience in mind.
Combating burnout.
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.